• Open Barbers are delighted to welcome Massage by Mercedez

    Open Barbers are delighted to welcome Massage by Mercedez. Every Tuesday and Sunday, starting Tuesday 5th July 2016, Mercedez Gonzalez will be working from the back room at Open Barbers which is discrete, sound proofed and fully equipped. Prices operate on a sliding scale (£25 – 60 for 1 hour) and bookings are made by

    Read more…


  • Free workshops at Open Barbers

    ***FREE WORKSHOPS AT OPEN BARBERS, TICKETS RELEASED TODAY!*** We will be hosting Three workshops as part of Amy Pennington’s residency at Open Barbers. Please email Amy at lookbookob@gmail.com on this date to reserve your place – places are limited so get in there quick! 1) Scottee on Saturday 2nd July ‘Let’s Be Angry’ Scottee invites any aspiring

    Read more…


  • Open Barbers open TODAY!

    Open Barbers opens TODAY! Tuesday 3rd May 2016, 1 – 9pm. 4 Clunbury Street, London, N1 6TT. Can’t wait to welcome you! 

    Read more…


  • Our new space opens on Tuesday 3rd May 2016!

    We are excited and nervous to be on the final countdown of our renovations as our new space at 4 Clunbury Street, London, N1 6TT opens on Tuesday 3rd May 2016! Over the past week, our builders Loz, Milo and PJ finished all their jobs fitting sound proofed acoustic glass, plastering their beautiful walls and

    Read more…


  • One week until we open

    With one week to go until we open on Tuesday 3rd May 2016, we’ve seen an amazing final push from the builders and our super generous volunteers working with us to sort out the walls and the floor and all the essentials!

    Read more…


  • Painting the new salon

    Here’s some of our wonderful volunteers painting the new salon over the past 2 weeks, which were weeks 5 – 6 of the renovation process. We are so grateful to each and every one of you! xxx

    Read more…


  • Renovation Update, Weeks 5 – 6, Monday 4th – Sunday 17th April

    Most of the main building work is now complete in the space! The toilet has been plumbed in and the grab rails are up. The doors to the toilet and the back room have been hung. We just need to finish the toilet, add an interior window, and add the lights and electrical sockets. There

    Read more…


  • Renovation visual updates! Week 5

    Renovation visual updates! 6th – 11th April, week 5 Volunteers galore this week! So many hands on deck have made the sanding, wallpaper removal and paint stripping breeze by… thank you everyone! The building dream team are nearing the completion of their role, working with Ralph the plumber to install our new accessible toilet. Here

    Read more…